Поиск

Merck Serono SPA

— n° 2 GX 2000 12 bar— n° 2 GSS 72/2X Глобальная система безопасности 72 ч— n° 2 ECXV-I 15-20 (inox — tipo B) 1500000-2000000 kcal/h — SIXEN 3500 — GX 2000— n° 2 Клапан питательный модуляционный двухходовой электрический и насосы с инвертером— n° 2 Двухступенчатая прогрессивная газовая горелка, с низким выбросом оксидов азота— n° […]

Ospedale di Borgo Roma, Verona (IT)

— n° 2 GX 6000 12 bar export— n° 2 ECXV 60-70 (типа B) 6000000-7000000 kcal/h — GX 6000— n° 2 Группа модуляции подачи питательной воды, двухходовой клапан DN 40 GX 6000-8000— n° 1 GSX 6000 P 12 bar export— n° 1 ECO-G 6 (B) — GSX 5000— n° 1 Группа модуляции подачи питательной воды, […]

Ospedale di Cattinara e Ospedale Maggiore, Trieste (IT)

— n° 2 TNOX 3500 BT COND— n° 2 TNOX 6000 BT COND— n° 2 GSS 72 Глобальная система безопасности 72 ч для котлов на перегретой воде— n° 2 ASGX EN 3500— n° 1 GREENOx BT COND 300

Caseificio Sanguedolce (II°)

— n° 1 GSX 3000 12 bar— n° 1 GSS 72/2X Глобальная система безопасности 72 ч— n° 1 ECO-G 4 (A) — GSX 3000 — P 3500

Cartiera, Condino (TN)

— n° 1 GX 15000 15 bar export— n° 1 Модуляционная газовая горелка— n° 1 GSS 24/0 Глобальная Система Езопасности— n° 1 Группа модуляции подачи питательной воды, двухходовой клапан DN 50 GX 9000-15000— n° 1 Группа модуляции питательной воды с электрическим клапаном DN 40 (паропроизводительность 10240-13600 кг/ч)

Fontanafredda Srl

THE PROJECT The initial request of the customer involved the resolution of the problem of having to completely modernize the existing thermal power station by differentiating the fluid carriers distributed according to the needs of the case, less steam and more hot water. Previously there was only one steam boiler with exchangers that satisfied the […]

Aboca SPA

THE PROJECT The initial request of the customer involved the resolution of the problem of having a steam boiler destined for the research and development area, delocalised with respect to the primary steam distribution. The thermal power plant was built from scratch with a sandwich panel structure and positioned inside a GSX series steam boiler […]

Ferrari & Franceschetti SPA

THE PROJECT The initial request of the customer involved the resolution of the problem of having a back-up steam boiler to the existing one that had a producibility adequate to the needs and a high efficiency to reduce consumption. Previously, the plant consisted of an old-generation, flame-reversing steam boiler, which, due to age limitations, required […]

RSA di Ciriè (ASL 4 Torino)

— n° 2 Monolite 270 GT— n° 2 Панель управления с сенсорным экраном eterm ®— n° 2 Нейтрализатор

Brianza Salumi SRL

— n° 1 ECOVAPOR 1700 ECS72 Термическая группа 1700 кг/ч 12 бар— n° 1 CMMS Ecovapor — (Coincidence Monitoring & Management System)