Merck Serono SPA
– n° 2 GX 2000 12 bar– n° 2 GSS 72/2X – Système de sécurité globale.– n° 2 ECXV-I 15-20 (inox – tipo B) 1500000-2000000 kcal/h – SIXEN 3500 – GX 2000– n° 2 Système de regulation de niveau modulant vanne à 2 voies électrique et 2 pompes avec variateur– n° 2 Brûleur gaz naturel […]
Ospedale di Borgo Roma, Verona (IT)
– n° 2 GX 6000 12 bar export– n° 2 ECXV 60-70 (type B) 6000000-7000000 kcal/h – GX 6000– n° 2 Systeme de reglage du niveau modulant DN 40 GX 6000-8000– n° 1 GSX 6000 P 12 bar export– n° 1 ECO-G 6 (B) – GSX 5000– n° 1 Systeme de reglage du niveau modulant […]
Ospedale di Cattinara e Ospedale Maggiore, Trieste (IT)
– n° 2 TNOX 3500 BT COND– n° 2 TNOX 6000 BT COND– n° 2 GSS 72 KIT Système de sécurité globale 72 H Eau Surchauffée– n° 2 ASGX EN 3500– n° 1 GREENOx BT COND 300
Caseificio Sanguedolce (II°)
– n° 1 GSX 3000 12 bar– n° 1 GSS 72/2X – Système de sécurité globale.– n° 1 ECO-G 4 (A) – GSX 3000 – P 3500
Anastasi Srl
– n° 1 SIXEN 500 12 bar
Cartiera, Condino (TN)
– n° 1 GX 15000 15 bar export– n° 1 Brûleur gaz naturel modulant– n° 1 GSS 24/0 systeme de securite globale 24H– n° 1 Systeme de reglage du niveau modulant DN 50 GX 9000-15000– n° 1 Systeme de reglage du niveau modulant DN 40 (10240-13600 kg/h vapeur)
Fontanafredda Srl
THE PROJECT The initial request of the customer involved the resolution of the problem of having to completely modernize the existing thermal power station by differentiating the fluid carriers distributed according to the needs of the case, less steam and more hot water. Previously there was only one steam boiler with exchangers that satisfied the […]
Aboca SPA
THE PROJECT The initial request of the customer involved the resolution of the problem of having a steam boiler destined for the research and development area, delocalised with respect to the primary steam distribution. The thermal power plant was built from scratch with a sandwich panel structure and positioned inside a GSX series steam boiler […]
Ferrari & Franceschetti SPA
THE PROJECT The initial request of the customer involved the resolution of the problem of having a back-up steam boiler to the existing one that had a producibility adequate to the needs and a high efficiency to reduce consumption. Previously, the plant consisted of an old-generation, flame-reversing steam boiler, which, due to age limitations, required […]
Centrale Termica Prefabbricata – Acqua Surriscaldata
– n° 1 ASX 1000 5 bar– n° 1 GSS 72 KIT Système de sécurité globale 72 H Eau Surchauffée
RSA di Ciriè (ASL 4 Torino)
– n° 2 Monolite 270 GT– n° 2 Coffret de commande chaudière avec carte électronique eterm ®– n° 2 Neutralisateur
Brianza Salumi SRL
– n° 1 ECOVAPOR 1700 ECS72 Gruppo Termico 1700 kg/h 12 bar– n° 1 CMMS Ecovapor – (Coincidence Monitoring & Management System)