THE PROJECT
The initial request of the customer involved the resolution of the problem of having a back-up steam boiler to the existing one that had a producibility adequate to the needs and a high efficiency to reduce consumption.
Previously, the plant consisted of an old-generation, flame-reversing steam boiler, which, due to age limitations, required repairs that were too expensive to deal with. In addition, a relatively recent steam boiler with 3 t/h producibility at three-pass steam boiler.

THE SOLUTION
After careful analysis, ICI Caldaie proposed a GSX series boiler with a power of 2.5 t/h, lower than the one installed, equipped with a 1st stage economiser, for pre-heating of the feed water and an additional 2nd stage for water pre-heating of the water collection tank. To date the customer uses this generator as primary with considerable benefits on consumption and plant management costs.

Calderas instaladas

GX

La gama GX presenta generadores de vapor monobloque con prestaciones excelentes, diseñados para ofrecer la máxima garantía de...

Producción de vapor: 1700 ÷ 32000 kg/h

Poder útil: 1163 ÷ 17442 kW

Presión de diseño: 12 o 15 bar

Eficiencia: 90,0 %

¿Le gustaría saber más?